A company constructed a new warehouse. Costs incurred were: raw materials N50 million, direct labor N20 million, architect fees N2 million, general administrative overheads N5 million, and staff training costs for operating the new facility N3 million. What is the initial cost of the warehouse to be capitalized under IAS 16?
- AN72 million
- BN77 million
- CN80 million
- DN70 million