A project team holds a charrette at the beginning of a tenant improvement project with the owner, architect, MEP engineer, contractor, and facility manager. When is this approach MOST beneficial?
- ADuring construction to resolve field conflicts
- BDuring pre-design before major design decisions are finalized
- CDuring final documentation to coordinate submission materials
- DDuring post-occupancy to evaluate performance