Under OBC 9.23.9.6., where a non-loadbearing partition parallel to the floor joists is supported by the floor, and the joists are not doubled, what structural action is required?
- AThe joist spacing must be reduced to 300 mm
- BSolid blocking must be installed between the joists at not more than 1.2 m spacing
- CNo action is required as long as the joist span is under 3 m
- DHangers must be used at the ends of the partition joists