What does WBS stand for in project planning, and what is its primary purpose?
Planning Fundamentals
Question · Easy
Earned value on top: the fight song
Short
In a Work Breakdown Structure, what is the lowest level of decomposition called?
Chapter 0: Introduction & AACE PSP Exam Structure
0.1 Current AACE PSP Exam, Eligibility, and Certification Facts
Study guide
What does the OBS (Organizational Breakdown Structure) define on a project?
Trades Exam Prep Podcast
Listen on Spotify
Podcast
What is a Resource Breakdown Structure (RBS) used for?
Which AACE Recommended Practice provides guidance on Forensic Schedule Analysis?
Claims Forensic Analysis
Question · Medium
The longest way home
In Critical Path Method (CPM), how is Total Float calculated for an activity?
Scheduling Techniques
0.2 Planning and Scheduling Professional Roles and Competencies
How is Free Float calculated between a predecessor activity and its successor in a Finish-to-Start relationship with a lag?
Activities A (5 days) → B (10 days) → C (4 days) form a single chain with FS relationships and no lags. What are the Early Start (ES) and Early Finish (EF) of activity C, assuming the project starts on day 0?
What does a backward pass through a CPM network calculate?
Which set of relationships is supported by Precedence Diagramming Method (PDM) but NOT by Arrow Diagramming Method (ADM/AOA)?
0.3 Cost Engineering and Scheduling Terminology per RP 10S-90
What is a 'fragnet' in scheduling and forensic analysis?
What is 'laddering' (or a 'ladder' relationship) used for in network scheduling?
PERT estimates an activity duration as Optimistic = 4 days, Most Likely = 10 days, Pessimistic = 22 days. What is the PERT (beta) expected duration?
What is the primary visual purpose of a Gantt chart?
Chapter 1: Scope Definition & Planning Fundamentals
1.1 Work Breakdown Structure (WBS) Architecture & RP 33R-15
What is the difference between resource leveling and resource smoothing?
Resource Planning Leveling
What does a resource histogram display?
What is a 'lookahead schedule' and how is it typically used in construction?
An S-curve in project controls typically plots which of the following?
1.2 Organization & Resource Breakdown Structures (OBS, RBS, RAM)
What is a baseline schedule, and what is its role in schedule control?
Schedule Control Monitoring
Which AACE Recommended Practice provides guidance on Time Impact Analysis (TIA) as applied in construction?
When performing a prospective Time Impact Analysis (TIA) per RP 52R-06, into which schedule is the delay fragnet inserted?
Question · Hard
What is the role of Monte Carlo simulation in schedule risk analysis?
Schedule Risk Analysis
1.3 Project Planning and Activity-Logic Development
If a Monte Carlo schedule risk analysis reports a P80 completion date of December 15 and a P50 of November 1, what is the implied schedule contingency to commit to the P80?
Which formula correctly defines Schedule Performance Index (SPI) in earned value management?
Earned Schedule Value
How does Earned Schedule (ES) improve on traditional EV-based schedule metrics late in the project?
What does scope definition produce that the WBS organizes?
1.4 Contract Requirements and Delivery Constraints
In a deliverable-oriented WBS, which item is most appropriate at WBS level 2?
Per AACE RP 14R-90, which skill is identified as a core competency of a project planning engineer?
What is the difference between an activity and a work package?
Which of the following is a valid characteristic of a 'deliverable' in project planning?
1.5 Stakeholder Identification, Needs, and Plan Review
An activity has Early Start = 10, Early Finish = 15, Late Start = 14, Late Finish = 19. What is its Total Float?
Two paths through a network have the following durations: Path 1 = 30 days, Path 2 = 25 days. The project's required completion is day 30. What is the total float on Path 2?
Per AACE RP 49R-06, which method is the primary basis for identifying the critical path?
In a Start-to-Start (SS) relationship with a 3-day lag, when can the successor start relative to the predecessor?
1.6 Constructability Methods and Value Engineering
Why does AACE generally caution against the overuse of constraints (e.g., 'Start No Earlier Than') in CPM schedules?
Which AACE Recommended Practice covers Schedule Update Review?