If a Material Work Package has an EV technique of 'apportioned effort' to an installation work package, and the installation WP has EV = $200,000 against a base BAC of $400,000, while the material WP has BAC = $80,000, the material EV is:
- A$40,000
- B$80,000
- C$160,000
- D$200,000