6.3 Predictive Project Controls and Artifacts

Key Takeaways

  • Change control ensures that only approved changes modify project baselines through the Perform Integrated Change Control process
  • The Change Control Board (CCB) is a formally constituted group responsible for reviewing, evaluating, approving, deferring, or rejecting changes
  • Configuration management ensures that descriptions of the project product are correct and complete through identification, status accounting, verification, and auditing
  • Key predictive artifacts include the project charter, project management plan, work performance reports, and lessons learned register
  • Earned Value Management is the primary performance measurement tool for predictive projects
Last updated: March 2026

Predictive Project Controls and Artifacts

In predictive project management, maintaining control over scope, schedule, cost, and quality is critical. This section covers the control mechanisms and key artifacts used in plan-based projects.

Integrated Change Control

Perform Integrated Change Control is the process of reviewing all change requests, approving changes, and managing changes to deliverables, project documents, and the project management plan.

Change Control Process

  1. Change request is submitted — Anyone can submit, but it must be documented
  2. Change request is logged — Recorded in the change log with a unique ID
  3. Impact analysis — Assess the impact on scope, schedule, cost, quality, risk, and resources
  4. Review by CCB — The Change Control Board reviews and decides
  5. Decision — Approve, reject, defer, or request more information
  6. Implementation — If approved, update the project management plan and baselines
  7. Communication — Notify stakeholders of the decision and any impacts

Change Control Board (CCB)

The CCB is a formally constituted group responsible for reviewing and deciding on proposed changes:

AspectDetails
MembersSponsor, PM, key stakeholders, subject matter experts
AuthorityCan approve, reject, or defer changes
When activeOnce the project baselines are established
DocumentationMaintains a change log of all requests and decisions

Types of Changes

TypeDescription
Corrective ActionAligns future performance with the project management plan
Preventive ActionReduces the probability or impact of a potential future variance
Defect RepairModifies a non-conforming deliverable to meet requirements
UpdateChanges to formally controlled documents, plans, or baselines

Configuration Management

Configuration management ensures that the descriptions and functional/physical characteristics of the project product, service, or result are correct and complete.

Configuration Management Activities

ActivityPurpose
Configuration IdentificationIdentify and document the functional and physical characteristics of items
Configuration Status AccountingTrack the status of configuration items and changes
Configuration Verification and AuditingEnsure configuration items conform to requirements

Key Predictive Project Artifacts

ArtifactPurposeCreated During
Project CharterFormally authorizes the projectInitiating
Project Management PlanComprehensive guide for project executionPlanning
Work Performance DataRaw observations during executionExecuting
Work Performance InformationAnalyzed data in contextMonitoring & Controlling
Work Performance ReportsCompiled information for decision-makingMonitoring & Controlling
Change LogRecords all change requests and their statusThroughout
Issue LogTracks issues and their resolutionThroughout
Lessons Learned RegisterDocuments what worked and what didn'tThroughout
Final ReportSummarizes project performance and outcomesClosing

Performance Reporting

Work Performance Data → Information → Reports

Work Performance Data (raw observations)
  ↓ Analysis and context
Work Performance Information (analyzed data)
  ↓ Compilation and formatting
Work Performance Reports (stakeholder communications)
LevelExample
Data47 of 60 activities complete, $450,000 spent
InformationSPI = 0.92 (behind schedule), CPI = 1.05 (under budget)
ReportStatus report showing schedule recovery plan with cost forecast

Variance and Trend Analysis

In predictive projects, variances from the baseline are key control signals:

VarianceFormulaMeaning
Schedule VarianceSV = EV - PVHow far ahead/behind schedule
Cost VarianceCV = EV - ACHow far under/over budget
Scope VarianceComparison of completed vs. planned deliverablesHow scope is tracking

Trend analysis examines performance over time to:

  • Predict future performance based on current trends
  • Identify patterns that may require corrective action
  • Support Estimate at Completion (EAC) calculations
Test Your Knowledge

Who is responsible for approving or rejecting change requests in a predictive project?

A
B
C
D
Test Your Knowledge

Which type of change aligns future project performance with the project management plan?

A
B
C
D
Test Your KnowledgeOrdering

Place the work performance levels in order from raw data to stakeholder-ready output:

Arrange the items in the correct order

1
Work Performance Reports
2
Work Performance Data
3
Work Performance Information
Test Your Knowledge

Configuration management primarily ensures that:

A
B
C
D