All Practice Exams

100+ Free AACE CCP Practice Questions

Pass your AACE Certified Cost Professional exam on the first try — instant access, no signup required.

✓ No registration✓ No credit card✓ No hidden fees✓ Start practicing immediately
100+ Questions
100% Free
1 / 100
Question 1
Score: 0/0

According to the AACE International Recommended Practice 18R-97, which estimate class represents the lowest level of project definition (typically 0%–2% complete) and is used for concept screening?

A
B
C
D
to track
2026 Statistics

Key Facts: AACE CCP Exam

120

MCQ Questions

AACE International

5 hrs

MCQ Time Limit

AACE International

10 Domains

TCM Framework

AACE TCM Framework

70%

Passing Score

AACE handbook

4 yrs

Experience (with degree)

AACE eligibility

100+

Free Practice Questions

OpenExamPrep question bank

The CCP exam is a 5-hour, 120-question multiple-choice test plus a technical paper, covering the AACE TCM Framework: cost estimating (Class 1-5 estimates, contingency), cost engineering economics (PV, NPV, IRR, MACRS), project cost management (EVM with CPI/SPI/EAC/TCPI), planning and scheduling (CPM, PERT), project management process, quality management (cost of quality), resource management (learning curves), procurement (FFP, FPIF, CPFF, CPIF, T&M, GMP, IPD contracts), risk management (qualitative, Monte Carlo), and TCM framework. Both English and metric units are tested.

Sample AACE CCP Practice Questions

Try these sample questions to test your AACE CCP exam readiness. Each question includes a detailed explanation. Start the interactive quiz above for the full 100+ question experience with AI tutoring.

1According to the AACE International Recommended Practice 18R-97, which estimate class represents the lowest level of project definition (typically 0%–2% complete) and is used for concept screening?
A.Class 1
B.Class 3
C.Class 4
D.Class 5
Explanation: Class 5 estimates are produced at the earliest level of project definition (0%–2% complete) and are typically used for concept screening, feasibility, or order-of-magnitude purposes. They have the widest accuracy ranges (often -50% to +100%) and the lowest preparation effort. As project definition matures, classes progress toward Class 1, which is the most definitive (65%–100% complete).
2In total cost management, which cost category includes labor, materials, equipment, and subcontracts that are incurred directly by the project work activities?
A.Indirect costs
B.Direct costs
C.Sunk costs
D.Opportunity costs
Explanation: Direct costs are costs that can be specifically and exclusively traced to a particular project activity, deliverable, or work package. Typical direct costs include craft labor, permanent materials, installed equipment, and subcontracted scope. They are distinguished from indirect costs (which support multiple activities, such as project management, site overhead, or general office expenses) by their traceability to a single cost object.
3Contingency, as defined by AACE, is intended to cover which of the following?
A.Scope changes outside the current project baseline
B.Identified risks and known-unknowns within the defined scope
C.Force majeure events such as war or natural disaster
D.Profit margin and shareholder return
Explanation: AACE defines contingency as an amount added to an estimate to allow for items, conditions, or events whose state, occurrence, or effect is uncertain but that experience shows will likely result in additional cost — i.e., 'known-unknowns' within the defined scope. Contingency does not cover scope changes (those use change management/management reserve) or extraordinary force majeure events (often handled through allowances or escalation).
4Which estimating method develops cost by aggregating the cost of each individual component, work package, or activity from the bottom up?
A.Parametric estimating
B.Analogous (top-down) estimating
C.Detailed (definitive) estimating
D.Order-of-magnitude estimating
Explanation: Detailed (or definitive) estimating builds total project cost by quantifying each work package or activity, applying unit rates for labor, material, and equipment, and aggregating bottom-up. It requires substantial design completion and is associated with AACE Class 1 or Class 2 estimates. Parametric and analogous methods are top-down approaches used at lower levels of project definition.
5An owner asks for a Class 3 estimate. According to AACE 18R-97, what level of project definition is typically required, and what is the primary use?
A.0%–2% definition; concept screening
B.1%–15% definition; study or feasibility
C.10%–40% definition; budget authorization, funding, or control baseline
D.65%–100% definition; check estimate or bid evaluation
Explanation: Per AACE 18R-97, a Class 3 estimate is prepared at 10%–40% project definition and is most commonly used to authorize budget, support funding decisions, or establish a project control baseline. Typical accuracy ranges fall around -20% to +30%, although the actual range depends on the industry and risk profile.
6A future cash flow of $100,000 is to be received in 5 years. At an annual discount rate of 8%, what is its present value (rounded)?
A.$68,058
B.$74,074
C.$92,593
D.$108,000
Explanation: Present Value = FV / (1 + i)^n = 100,000 / (1.08)^5. (1.08)^5 ≈ 1.4693, so PV ≈ 100,000 / 1.4693 ≈ $68,058. This is the (P/F, 8%, 5) single-payment present-worth factor in engineering economics.
7An asset costs $50,000 with a salvage value of $5,000 after a 5-year useful life. Using straight-line depreciation, what is the annual depreciation expense?
A.$9,000
B.$10,000
C.$11,000
D.$45,000
Explanation: Straight-line depreciation = (Cost − Salvage) / Useful Life = ($50,000 − $5,000) / 5 = $9,000 per year. The depreciable base ($45,000) is spread evenly over the asset's life, regardless of usage pattern.
8A project has cash flows of -$100,000 at year 0, +$40,000 at years 1, 2, and 3. At a discount rate of 10%, what is the project's NPV (rounded)?
A.-$526
B.$0
C.-$526 with IRR > 10%
D.$5,000
Explanation: NPV = -100,000 + 40,000/(1.10)^1 + 40,000/(1.10)^2 + 40,000/(1.10)^3 = -100,000 + 36,364 + 33,058 + 30,053 ≈ -100,000 + 99,475 ≈ -$525. Because NPV is negative at 10%, the IRR is below 10% (the discount rate that drives NPV to zero is approximately 9.7%).
9Which depreciation method records higher expense in early years and lower expense in later years by applying a fixed rate (typically 200%) to the declining book value, ignoring salvage value until the book value approaches it?
A.Straight-line
B.Sum-of-the-years-digits
C.Double-declining balance (DDB)
D.Units-of-production
Explanation: Double-declining balance (DDB) applies twice the straight-line rate (200%) to the asset's book value each year. Because the book value declines, the depreciation expense decreases over time. Salvage value is not subtracted from the depreciable base; instead, depreciation stops once book value equals salvage. DDB is an accelerated method, recognizing more expense earlier in the asset's life.
10Under the U.S. Modified Accelerated Cost Recovery System (MACRS), which recovery period applies to most computers and office machinery?
A.3 years
B.5 years
C.7 years
D.10 years
Explanation: MACRS assigns 5-year recovery to computers, peripheral equipment, automobiles, light trucks, and certain office equipment. The standard MACRS classes are 3, 5, 7, 10, 15, 20, 27.5 (residential rental), and 39 (nonresidential real). The 5-year class also includes certain manufacturing technology and research equipment.

About the AACE CCP Exam

The AACE Certified Cost Professional (CCP) is AACE International's flagship total cost management credential, recognizing experienced practitioners who can plan, estimate, schedule, and control costs across the asset lifecycle. The CCP exam covers ten domains drawn from the AACE Total Cost Management (TCM) Framework: cost estimating, engineering economics, project cost management, planning and scheduling, project management process, quality management, resource management, procurement, risk management, and TCM overview. Candidates must hold a four-year industry-related degree plus 4 years of experience (or equivalent), submit a technical paper, and pass a 5-hour multiple-choice exam.

Assessment

120 multiple-choice questions plus a technical paper (memo) demonstrating real-world cost engineering experience

Time Limit

5 hours (MCQ) + technical paper submitted separately

Passing Score

70% (combined MCQ and technical paper)

Exam Fee

$525 AACE members / $690 non-members (AACE International)

AACE CCP Exam Content Outline

15%

Cost Engineering Economics

Time value of money (PV/FV/PMT), NPV, IRR, payback, equivalent annual cost, depreciation methods (straight-line, DDB, sum-of-years-digits, MACRS recovery periods 3/5/7/10/15/20), inflation/escalation, after-tax cash flow, and the depreciation tax shield.

12%

Cost Estimating

AACE 18R-97 Class 1-5 estimate classifications, direct vs. indirect costs, contingency vs. management reserve, parametric methods (six-tenths rule, Lang factors), location factors, and bottom-up definitive estimating.

12%

Project Cost Management

Cost baseline, time-phased budgets, cost accounts, ANSI/EIA-748 EVM standards, earned value formulas (PV, EV, AC, CV, SV, CPI, SPI, EAC, ETC, VAC, TCPI), and percent-complete techniques (0/100, 50/50, weighted milestones).

12%

Project Planning and Scheduling

CPM forward and backward passes, total float and free float, PERT three-point estimating with O-4M-P/6 mean and (P-O)/6 standard deviation, critical chain method, schedule compression via crashing and fast-tracking, and resource leveling vs. smoothing.

10%

Project Management Process

Initiating (project charter), planning (project management plan and subsidiary plans, WBS), executing, monitoring and controlling (integrated change control, performance measurement), and closing (final reports, lessons learned).

8%

Quality Management

Cost of quality (COQ) - prevention costs, appraisal costs, internal failure costs, external failure costs - quality assurance vs. quality control, Pareto analysis, and the conformance-vs-nonconformance trade-off.

8%

Resource Management

Productivity benchmarks, Wright/Crawford learning curves (90%, 85%, 80% rates), labor and equipment rate development, resource leveling vs. smoothing, and portfolio-level resource utilization.

8%

Procurement

Make-or-buy analysis, contract types and risk allocation: Firm Fixed Price (FFP), Fixed Price Incentive Fee (FPIF), Fixed Price with Economic Price Adjustment (FPEPA), Cost Plus Fixed Fee (CPFF), Cost Plus Incentive Fee (CPIF), Cost Plus Award Fee (CPAF), Time and Materials (T&M), Guaranteed Maximum Price (GMP), and Integrated Project Delivery (IPD); bid analysis and bonds.

8%

Risk Management

Risk identification, qualitative analysis (probability-impact matrix), quantitative analysis (Monte Carlo simulation, expected monetary value, decision trees), risk responses (avoid, transfer, mitigate, accept; exploit, share, enhance), and contingency vs. management reserve.

7%

Total Cost Management (TCM) Overview

AACE TCM Framework integrating Strategic Asset Management and Project Control through a Plan-Execute-Measure-Assess (PDCA) loop, asset lifecycle management, and the strategic-to-project handoff.

How to Pass the AACE CCP Exam

What You Need to Know

  • Passing score: 70% (combined MCQ and technical paper)
  • Assessment: 120 multiple-choice questions plus a technical paper (memo) demonstrating real-world cost engineering experience
  • Time limit: 5 hours (MCQ) + technical paper submitted separately
  • Exam fee: $525 AACE members / $690 non-members

Keys to Passing

  • Complete 500+ practice questions
  • Score 80%+ consistently before scheduling
  • Focus on highest-weighted sections
  • Use our AI tutor for tough concepts

AACE CCP Study Tips from Top Performers

1Master the AACE Total Cost Management (TCM) Framework structure: two integrated process areas (Strategic Asset Management and Project Control), each following a Plan-Execute-Measure-Assess loop. Most exam questions trace back to this hierarchy.
2Memorize the AACE 18R-97 estimate classifications cold: Class 5 (concept screening, 0-2% definition) → Class 4 (study/feasibility, 1-15%) → Class 3 (budget/control, 10-40%) → Class 2 (control, 30-70%) → Class 1 (check/bid, 65-100%). Know typical accuracy ranges.
3Drill engineering economics formulas until they are automatic: PV = FV/(1+i)^n; NPV = sum CF/(1+r)^t; (P/A, i, n) = [(1+i)^n − 1]/[i(1+i)^n]; capital recovery (A/P) = i(1+i)^n / [(1+i)^n − 1]; effective annual rate = (1 + i_nom/m)^m − 1.
4Memorize MACRS recovery periods: 3-yr (rent-to-own, breeding stock); 5-yr (computers, autos, light trucks, certain mfg equipment); 7-yr (office furniture, most other equipment); 10-yr (vessels, agricultural structures); 15/20-yr (utilities, farm buildings); 27.5-yr (residential rental); 39-yr (nonresidential real).
5Earned value formulas to memorize: CPI = EV/AC; SPI = EV/PV; CV = EV − AC; SV = EV − PV; EAC (typical) = BAC/CPI; EAC (cost AND schedule) = AC + (BAC−EV)/(CPI×SPI); TCPI = (BAC−EV)/(BAC−AC). Always put EV on top — it is the work earned.
6Memorize contract type acronyms and risk allocation. Seller bears most risk: FFP > FPIF > FPEPA > T&M > CPIF > CPAF > CPFF. Know GMP (cost-reimbursable to a cap with shared savings) and IPD (multi-party shared risk/reward).
7Drill PERT formulas: tE = (O + 4M + P)/6 mean and σ = (P − O)/6 standard deviation. Sum activity variances along the critical path to estimate project completion variance. Three-point estimates can also use triangular distributions in Monte Carlo.
8Practice cost-of-quality categorization: prevention (training, planning) and appraisal (inspection, testing) are conformance costs; internal failure (rework, scrap) and external failure (warranty, recalls) are nonconformance. Investments in prevention typically lower total COQ.
9Wright learning curve rule: each doubling of cumulative output reduces unit time by the learning rate. 90% curve, 100 hr first unit → 90 hr (2nd) → 81 hr (4th) → 72.9 hr (8th). Steeper curves (70-80%) apply to highly repetitive automated work.
10Write the technical paper early. AACE requires a real project example demonstrating TCM principles. Allow 4-6 weeks for drafting, peer review, and revisions. Papers that are too short, generic, or fail to apply specific TCM concepts will be rejected even if the MCQ is passed.

Frequently Asked Questions

What is the AACE CCP certification?

The Certified Cost Professional (CCP) is AACE International's flagship credential for experienced total cost management practitioners. It validates expertise across estimating, engineering economics, project control, scheduling, procurement, quality, and risk over the asset lifecycle.

What are the CCP eligibility requirements?

Candidates need a 4-year industry-related college/university degree plus 4 years of experience, OR 8 years of experience without a degree. They must submit a technical paper demonstrating practical application of cost engineering principles, sign the AACE Code of Ethics, and pass the multiple-choice exam.

How is the CCP exam structured?

The CCP exam is a 5-hour computer-based test of 120 multiple-choice questions delivered through Pearson VUE, plus a separately submitted technical paper (typically 2,500 words) on a project the candidate worked on. Both must be passed for certification.

What is the CCP passing score?

AACE requires a minimum 70% combined score across the multiple-choice exam and the technical paper. Both components must demonstrate competency. Specific scoring rubrics for the technical paper evaluate clarity, application of TCM principles, and original analysis.

How much does the CCP exam cost?

The CCP application fee is $525 for AACE members and $690 for non-members. AACE membership is approximately $185 annually for full members. Retake fees apply if either component is failed. Costs are subject to change; verify on aacei.org.

How does the CCP differ from the AACE CEP?

The CCP is broader, covering the entire AACE Total Cost Management framework (10 domains spanning estimating, economics, scheduling, EVM, risk, procurement, quality). The CEP (Certified Estimating Professional) is specialized in cost estimating only. Many practitioners earn the CEP first, then pursue the CCP for senior-level recognition.

How long should I study for the CCP?

Most candidates dedicate 100-200 hours over 3-6 months. The AACE TCM Framework reference text, AACE Recommended Practices (especially 18R-97 estimate classification), engineering economics textbooks, and PMBOK are the primary study sources. Practice questions covering EVM, time-value-of-money, depreciation, and contract types are essential.

How do I maintain the CCP certification?

CCP certification is valid for 3 years. Recertification requires earning continuing education credits (typically 24-30 hours) in cost engineering or related areas, plus payment of recertification fees. AACE accepts coursework, conference attendance, teaching, publishing, and professional service for credit.